This week, IntraHealth will submit a monthly invoice summarizing travel costs in February and March along with paper timesheets for all work done prior to 05.2008.
This week, IntraHealth will submit a monthly invoice summarizing travel costs in February and March along with paper timesheets for all work done prior to 05.2008.


'''Weekly Update for 05.19.2008 to 05.25.2008'''
'''Weekly Update for 05.19.2008 to 05.25.2008'''
Line 60: Line 61:


We thank you for your feedback on the submitted monthly invoice and timesheets for all work done prior to 05.2008 and will make sure to follow your comments/requests.
We thank you for your feedback on the submitted monthly invoice and timesheets for all work done prior to 05.2008 and will make sure to follow your comments/requests.


Weekly Update for 05.26.2008 to 06.01.2008
Weekly Update for 05.26.2008 to 06.01.2008
Line 86: Line 88:


Scopes of work for travel for August and September are currently under development.
Scopes of work for travel for August and September are currently under development.


'''Weekly Update for 06.02.2008 to 06.08.2008'''
'''Weekly Update for 06.02.2008 to 06.08.2008'''
Line 113: Line 116:


With both sets of functional requirements now posted on the Wiki, we look forward to working with you to determine how we can shift them to “final” status per the requirements of the payment schedule. If possible, our finance team would like to submit an invoice for the initial $45k payment next week. Please note the use cases will inevitably change in small ways during the development process.
With both sets of functional requirements now posted on the Wiki, we look forward to working with you to determine how we can shift them to “final” status per the requirements of the payment schedule. If possible, our finance team would like to submit an invoice for the initial $45k payment next week. Please note the use cases will inevitably change in small ways during the development process.
'''Weekly Update for 06.09.2008 to 06.15.2008'''
*''Functional Requirements and Software Development''
The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.
Dave is working further on redoing the women’s contraceptive and children’s registry screens.
We are still discussing equipment and software platform specifications with Qualcomm.
*''Partner Updates''
Please let us know your availability to join our bi-weekly update calls scheduled with Qualcomm. The first call took place on 5 June and future calls will occur every other week on Thursdays at 11am EST. If you are available for the call next Thursday, it would be wonderful for everyone to touch base. You are of course invited to all future calls as well.
We look forward to your review and feedback on the press plan that has been approved by Qualcomm and is pending with SRA.
We look forward to your feedback on our idea to begin posting all project documents (including these weekly updates) on the Wiki.
*''Operations''
We hope to discuss with you how we can get SRA’s approval of both sets of functional requirements now posted on the Wiki so that we can shift them to “final” status per the requirements of the payment schedule. Please note the use cases will inevitably change in small ways during the development process.
'''Weekly Update for 06.16.2008 to 06.22.2008'''
*''Functional Requirements and Software Development''
The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.
Dave is working further on redoing the women’s contraceptive and children’s registry screens.
Following discussion on equipment and software platform specifications with QualComm, we have notified QualComm of our decision to use Java rather than Brew. 
*''Partner Updates''
It was great to have you on last week’s QualComm call. You are of course invited to all future calls as well.
We look forward to your feedback on our idea to begin posting all project documents (including these weekly updates) on the Wiki.
*''Operations''
We are currently working on formatting the use cases and the original forms so as to submit a complete report this or next week.
'''Weekly Update for 06.23.2008 to 06.29.2008'''
*''Functional Requirements and Software Development''
The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.
Dave is working further on redoing the women’s contraceptive and children’s registry screens.
*''Partner Updates''
Our hardware list has been sent to and reviewed by Qualcomm which expressed its interest in supporting this equipment selection.
 
*''Operations''
               
We are completing a final document which includes the use cases and the original forms and will submit it this week. 
Vanessa will be working on the draft and final Pilot Test Plans in the next few weeks as well as during her upcoming trip to Rwanda in late July, early August.
Vanessa will send you her scope of work and activity plan this week.
We hope you will find the Wiki a convenient tool to consult project documents.
'''Weekly Update for 06.30.2008 to 07.06.2008'''
*''Functional Requirements and Software Development''
Dave is working further on redoing the women’s contraceptive and children’s registry screens.
*''Partner Updates''
During her our bi-weekly call with Qualcomm, we discussed Vanessa’s upcoming travel as well as prepared upcoming discussions with Rwandatel.
*''Operations''
                 
We are completing a final document which includes the use cases and the original forms and will submit it this week. Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.
Vanessa is in touch with you concerning her trip to Kigali on the proposed dates of 25 July to 10 August.
'''Weekly Update for 07.07.2008 to 07.13.2008'''
*''Functional Requirements and Software Development''
The final document which includes the use cases and the original forms is being finalized and will be submitted to you on Thursday.  Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.
*''Partner Updates''
*''Operations''                 
An LMI press release is currently being drafted.
The Wiki is being populated with relevant project documents.
The Scope of Work for Vanessa’s trip to Kigali from 25 July to 10 August is the following:
Work on Sustainability Plan with Ministry and local staff
Meet with Qualcomm and Rwandatel to determine equipment and connectivity plan for pilot (Elizabeth from Qualcomm will be in Rwanda on August 4th, we have plans to meet with Rwandatel on August 6th)
Review use cases and resolve outstanding issues
Visit pilot sites with local staff and develop outline for Pilot Plan
Work on M&E plan with local staff (HQ M&E will also be in Kigali at this time)
Meet with Ministry stakeholders
Meet with local consultants able to provide implementation support
'''Weekly Update for 07.14.2008 to 07.20.2008'''
*''Functional Requirements and Software Development''
We have submitted the final document which includes the use cases, the original paper forms, and the latest indicators. We look forward to your feedback on this user friendly report.
Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.
Please note that the use cases will be evolving throughout the development process.
We will be working out final details on the contraceptive screen while Vanessa is in Rwanda.
*''Operations''                 
The LMI press release is currently being drafted.
Vanessa’s trip to Kigali from 25 July to 10 August has been approved by USAID and its planning is nearly finalized.
In recent travel planning developments, a meeting with the CEO of Rwandatel was confirmed for 6 August.
'''Weekly Update for 07.21.2008 to 07.27.2008'''
*''Functional Requirements and Software Development''
We have submitted a revised version of the use cases which also includes the original paper forms and the latest indicators. We look forward to your feedback and hope to be able to submit the invoice tied to this deliverable this week.
We will be generating a walkthrough of the entire menu-driven system using screen shots. This will be used during the Rwandatel meeting. We will also post a copy on the wiki.
The proposed contraceptive screens will collect information regarding contraceptive methods used during the current and previous months. This section will also collect information for planned methods for the coming month. It will be possible to select multiple methods.
While in Kigali, Vanessa will be re-testing internet speeds on EV-DO devices. If speeds are acceptable, we will use a mobile compatible web interface for the menu driven system.
Vanessa will also be investigating the in-country hardware options with an eye towards this web-interface direction.
The sustainability plan, pilot plan, M&E plan and press release are underway and are being developed collaboratively with Twubakane and Ministry staff while Vanessa is in Kigali.
*''Operations''
                           
Vanessa is in Kigali from 25 July to 10 August.
The meeting with the CEO of Rwandatel has been confirmed for 6 August at 11am. The meeting will include representatives from the MOH, Twubakane and Qualcomm. Elizabeth Migwalla from Qualcomm will be joining Vanessa in Rwanda during the week of August 4th. The meeting goal is to secure support from Rwandatel for equipment and connectivity.
Our contracts team is wondering if we need to amend the contract to reflect the later delivery date of the revised use cases. What are your thoughts?

Revision as of 10:06, 4 August 2008

Weekly Update for 05.05.2008 to 05.11.2008

  • Functional Requirements and Software Development

We are still in the process of developing the Wiki. Once development starts the code and documentation for the application will be available on this Wiki. The option to change the information will be available to all who request access. We will provide the link in next week’s weekly update.

The voice prompt system requirements are completed and will be posted on the Wiki next week.

The menu driven system requirements will follow.

  • Partner Updates

As you probably read in her email from 05.13.2008, Vanessa has worked with Qualcomm on a press plan.

Qualcomm hopes to announce our partnership at the Global Health Council at the end of May, if you agree.

  • Operations

Internally, we submitted paper timesheets for all work done prior to 05.2008 and IntraHealth’s contracts unit will submit them to SRA along with monthly invoices.


Weekly Update for 05.12.2008 to 05.18.2008

  • Functional Requirements and Software Development

The LMI Wiki on which we will post the code and the documentation for the applications has been developed and can be found at: http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative The draft for the voice prompt system requirements has been posted on the Wiki. The draft for the menu driven system requirements will be posted on the Wiki by the end of this week.

  • Partner Updates

Dave and Vanessa will be in Washington, DC from May 27 to 31 for Global Health Council. If Kim is in town that week, they would love to stop by and say hello.

The press plan has been approved by Qualcomm and is pending with SRA.

  • Operations

This week, IntraHealth will submit a monthly invoice summarizing travel costs in February and March along with paper timesheets for all work done prior to 05.2008.


Weekly Update for 05.19.2008 to 05.25.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements is slightly delayed and will be posted on the Wiki during the week of 26 May.

Equipment specifications are currently under development. A draft will be posted on Wiki in early June.

We hope you have had the chance to view the LMI Wiki on which we are posting the code and the documentation for the applications (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and we look forward to your feedback on the Wiki itself as well as on the voice prompt system requirements which have been posted there.

  • Partner Updates

Dave and Vanessa are in Washington, DC from May 27 to 31 for Global Health Council. Please call or email if SRA staff are available for a quick meeting. Vanessa’s mobile number is 919 616 3482 and Dave’s mobile number is 919 260 9158.

Bi-weekly update calls are scheduled with Qualcomm. The first call will be on 2 June. Linda Lee is the new project representative from Qualcomm.

We look forward to your review and feedback on the press plan that has been approved by Qualcomm and is pending with SRA.

  • Operations

Scopes of work for travel for August and September are currently under development.

We thank you for your feedback on the submitted monthly invoice and timesheets for all work done prior to 05.2008 and will make sure to follow your comments/requests.


Weekly Update for 05.26.2008 to 06.01.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements will be posted on the Wiki during this week.

We look forward to your review and feedback on the requirements for voice prompt system. These are posted on the Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative).

Equipment specifications are currently under development. A draft will be posted on Wiki in early June.

  • Partner Updates

Dave and Vanessa were very glad to meet you last week during their time in DC for Global Health Council.

Dave gave a talk on Open Source and Community Building and mentioned LMI at a roundtable at Global Health Council.

Bi-weekly update calls are scheduled with Qualcomm. The first call has been rescheduled for 5 June—please let us know if you will be back in town and would like to participate.

We look forward to your review and feedback on the press plan that has been approved by Qualcomm and is pending with SRA.

We are thinking about posting all project documents (including weekly updates) on the Wiki. This is a process we have already used in Uganda and which turned out to be successful there. We will go ahead and begin posting information this week. Please let us know if this raises any issues for you.

  • Operations

Scopes of work for travel for August and September are currently under development.


Weekly Update for 06.02.2008 to 06.08.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements are now posted on Wiki http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative

We look forward to your review and feedback on the requirements for the voice prompt system. These are also posted on the Wiki.

Dave is currently working on redoing the women’s contraceptive and children’s registry screens. We are discussing equipment and software platform specifications with Qualcomm.

  • Partner Updates

Bi-weekly update calls are scheduled with Qualcomm. The first call took place on 5 June and future calls will occur every other week on Thursdays at 11am EST. If you are available for the call next Thursday, it would be wonderful for everyone to touch base. You are of course invited to all future calls as well based on your availability.

We look forward to your review and feedback on the press plan that has been approved by Qualcomm and is pending with SRA.

We received an email from Judy Payne requesting an update on LMI progress. We will update the activity timeline and also forward a general update to her this week. We will be sure to copy you. Currently it looks like she will be in Rwanda at the end of June. She will be reviewing several projects underway—LMI among them.

We will begin posting all project documents (including these weekly updates) on the Wiki. As we mentioned in last week’s update, this is a process we have already used in Uganda and which turned out to be successful there. Please let us know if this raises any issues for you.

  • Operations

Scopes of work for travel for August and September are currently under development.

With both sets of functional requirements now posted on the Wiki, we look forward to working with you to determine how we can shift them to “final” status per the requirements of the payment schedule. If possible, our finance team would like to submit an invoice for the initial $45k payment next week. Please note the use cases will inevitably change in small ways during the development process.


Weekly Update for 06.09.2008 to 06.15.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.

Dave is working further on redoing the women’s contraceptive and children’s registry screens.

We are still discussing equipment and software platform specifications with Qualcomm.

  • Partner Updates

Please let us know your availability to join our bi-weekly update calls scheduled with Qualcomm. The first call took place on 5 June and future calls will occur every other week on Thursdays at 11am EST. If you are available for the call next Thursday, it would be wonderful for everyone to touch base. You are of course invited to all future calls as well.

We look forward to your review and feedback on the press plan that has been approved by Qualcomm and is pending with SRA.

We look forward to your feedback on our idea to begin posting all project documents (including these weekly updates) on the Wiki.

  • Operations

We hope to discuss with you how we can get SRA’s approval of both sets of functional requirements now posted on the Wiki so that we can shift them to “final” status per the requirements of the payment schedule. Please note the use cases will inevitably change in small ways during the development process.


Weekly Update for 06.16.2008 to 06.22.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.

Dave is working further on redoing the women’s contraceptive and children’s registry screens.

Following discussion on equipment and software platform specifications with QualComm, we have notified QualComm of our decision to use Java rather than Brew.

  • Partner Updates

It was great to have you on last week’s QualComm call. You are of course invited to all future calls as well.

We look forward to your feedback on our idea to begin posting all project documents (including these weekly updates) on the Wiki.

  • Operations

We are currently working on formatting the use cases and the original forms so as to submit a complete report this or next week.


Weekly Update for 06.23.2008 to 06.29.2008

  • Functional Requirements and Software Development

The draft for the menu driven system requirements and the voice prompt system are posted on Wiki (http://wiki.ihris.org/wiki/index.php/Last_Mile_Initiative) and awaiting your review and feedback.

Dave is working further on redoing the women’s contraceptive and children’s registry screens.

  • Partner Updates

Our hardware list has been sent to and reviewed by Qualcomm which expressed its interest in supporting this equipment selection.

  • Operations

We are completing a final document which includes the use cases and the original forms and will submit it this week.

Vanessa will be working on the draft and final Pilot Test Plans in the next few weeks as well as during her upcoming trip to Rwanda in late July, early August.

Vanessa will send you her scope of work and activity plan this week.

We hope you will find the Wiki a convenient tool to consult project documents.


Weekly Update for 06.30.2008 to 07.06.2008

  • Functional Requirements and Software Development

Dave is working further on redoing the women’s contraceptive and children’s registry screens.

  • Partner Updates

During her our bi-weekly call with Qualcomm, we discussed Vanessa’s upcoming travel as well as prepared upcoming discussions with Rwandatel.

  • Operations

We are completing a final document which includes the use cases and the original forms and will submit it this week. Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.

Vanessa is in touch with you concerning her trip to Kigali on the proposed dates of 25 July to 10 August.


Weekly Update for 07.07.2008 to 07.13.2008

  • Functional Requirements and Software Development

The final document which includes the use cases and the original forms is being finalized and will be submitted to you on Thursday. Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.

  • Partner Updates
  • Operations

An LMI press release is currently being drafted.

The Wiki is being populated with relevant project documents.

The Scope of Work for Vanessa’s trip to Kigali from 25 July to 10 August is the following:

Work on Sustainability Plan with Ministry and local staff

Meet with Qualcomm and Rwandatel to determine equipment and connectivity plan for pilot (Elizabeth from Qualcomm will be in Rwanda on August 4th, we have plans to meet with Rwandatel on August 6th)

Review use cases and resolve outstanding issues

Visit pilot sites with local staff and develop outline for Pilot Plan

Work on M&E plan with local staff (HQ M&E will also be in Kigali at this time)

Meet with Ministry stakeholders

Meet with local consultants able to provide implementation support


Weekly Update for 07.14.2008 to 07.20.2008

  • Functional Requirements and Software Development

We have submitted the final document which includes the use cases, the original paper forms, and the latest indicators. We look forward to your feedback on this user friendly report.

Once we have your approval on this document, we will submit an invoice for the first payment of $45,000.

Please note that the use cases will be evolving throughout the development process.

We will be working out final details on the contraceptive screen while Vanessa is in Rwanda.

  • Operations

The LMI press release is currently being drafted.

Vanessa’s trip to Kigali from 25 July to 10 August has been approved by USAID and its planning is nearly finalized.

In recent travel planning developments, a meeting with the CEO of Rwandatel was confirmed for 6 August.


Weekly Update for 07.21.2008 to 07.27.2008

  • Functional Requirements and Software Development

We have submitted a revised version of the use cases which also includes the original paper forms and the latest indicators. We look forward to your feedback and hope to be able to submit the invoice tied to this deliverable this week.

We will be generating a walkthrough of the entire menu-driven system using screen shots. This will be used during the Rwandatel meeting. We will also post a copy on the wiki.

The proposed contraceptive screens will collect information regarding contraceptive methods used during the current and previous months. This section will also collect information for planned methods for the coming month. It will be possible to select multiple methods.

While in Kigali, Vanessa will be re-testing internet speeds on EV-DO devices. If speeds are acceptable, we will use a mobile compatible web interface for the menu driven system.

Vanessa will also be investigating the in-country hardware options with an eye towards this web-interface direction.

The sustainability plan, pilot plan, M&E plan and press release are underway and are being developed collaboratively with Twubakane and Ministry staff while Vanessa is in Kigali.

  • Operations

Vanessa is in Kigali from 25 July to 10 August.

The meeting with the CEO of Rwandatel has been confirmed for 6 August at 11am. The meeting will include representatives from the MOH, Twubakane and Qualcomm. Elizabeth Migwalla from Qualcomm will be joining Vanessa in Rwanda during the week of August 4th. The meeting goal is to secure support from Rwandatel for equipment and connectivity.

Our contracts team is wondering if we need to amend the contract to reflect the later delivery date of the revised use cases. What are your thoughts?