The following are development goals only, not necessarily hard-and-fast deadlines, and are subject to change. Expect this calendar to be updated frequently as new priorities come up. Developers, feel free to annotate with your own goals. | The following are development goals only, not necessarily hard-and-fast deadlines, and are subject to change. Expect this calendar to be updated frequently as new priorities come up. Developers, feel free to annotate with your own goals. | ||
== Q2-Q3 2009 Goals (April-July 2009) == | |||
* Complete as many feature requests as possible in order of priority -- see bug tracker on Launchpad (all developers) | |||
* Customization support (roles/tasks/fields) (Carl/Luke) | |||
* Complete technical documentation and system administrator's manual (all developers) | |||
* Clean up and productize code, including easy-install packages (all developers) | |||
* Add in-context help and pop-up tips based on usability findings (developer TBD) | |||
* Provide direct way to offer technical support from the software (developer TBD) | |||
* Make user interface changes based on usability findings (developer TBD) | |||
=== iHRIS Survey (Tentative Product Idea) === | |||
iHRIS Survey would enable the user to create a form with all needed fields, enter the data into a flat database and then run reports on that data. The form could be customized to address a variety of issues: backlog data entry; a step solution to prepare and clean data before importing into the mature HRIS; enter people or facility survey data; or any other form/database needs. If approved, the first iteration can be released in Summer 2009. | |||
== Q1-Q2 2009 Goals (January-April 2009) == | |||
Version 3.3: | |||
* Duplicate records check (Carl) | |||
* Import/export data function for Manage/Qualify and synchronization for offline version (Carl/Luke) | |||
* Add asterisk to denote all required fields for easier data entry (Luke) | |||
* Revise explanatory text, instructions and some page views (Reports, Administer Database) based on usability findings (Carol/Luke) | |||
== Q3-Q4 2008 Goals (July 2008-December 2008) == | |||
* Enable translation support -- ''complete'' | |||
* Bug fixes/minor releases as needed -- ''complete'' | |||
== Q2 2008 Goals (April-June) == | |||
* Customized report builder for Manage/Qualify (Carl) -- ''complete and released in version 3.1'' | |||
* In-service training management module for iHRIS Manage completed (Carl) -- ''complete and released in version 3.1'' | |||
* iHRIS Plan version 1.0 (Luke) -- ''released'' | |||
== March 2008 Goals == | |||
* Post version 3.0 download packages for iHRIS Manage and Qualify (Carl/Luke) -- ''complete'' | |||
* Active Directory and other system integration for IntraHealth HRIS completed (Mark + internal ICT support) -- ''complete'' | |||
* Piloting and debugging of offline access (Mark) -- ''complete'' | |||
== February 2008 Goals == | |||
* iHRIS Plan specifications complete (Shannon) -- ''complete'' | |||
* Update and post v3.0 documentation and user's manuals for Manage and Qualify (Shannon) -- ''complete'' | |||
* Upgrade to version 3.0 of iHRIS Qualify in Uganda (Luke) -- ''complete'' | |||
* Upgrade to version 3.0 of iHRIS Manage in Rwanda (Mark) | |||
== | == January 2008 Goals == | ||
* Version 3.0 RC1 coding completed and made available for bug testing (Carl/Luke) -- ''complete'' | |||
* Test new features for version 3.0 of both systems (Shannon) -- ''complete'' | |||
== December 2007 Goals == | == December 2007 Goals == | ||
Line 19: | Line 66: | ||
* Workforce planning model approved for iHRIS Plan (Dykki) -- ''complete'' | * Workforce planning model approved for iHRIS Plan (Dykki) -- ''complete'' | ||
== | == November 2007 Goals == | ||
* Remaining first-round corrections to IntraHealth HRIS (Luke/Carl) -- ''complete'' | |||
* Post updated versions of all existing documentation to website/wiki (Shannon) -- ''complete'' | |||
* Complete specifications for training module for iHRIS Manage (Shannon) -- ''complete'' | |||
== | == October 2007 Goals == | ||
* | * Post the iHRIS Qualify Code to Launchpad (Luke) -- ''complete'' | ||
* Post new feature requests on Launchpad for Manage and Qualify (Shannon) -- ''complete'' | |||
* | * Print and export report/record feature (Carl) -- ''complete'' | ||
* | [[Category:Archived Pages]] | ||
Latest revision as of 11:49, 18 July 2013
Last update -- March 2009
The following are development goals only, not necessarily hard-and-fast deadlines, and are subject to change. Expect this calendar to be updated frequently as new priorities come up. Developers, feel free to annotate with your own goals.
Q2-Q3 2009 Goals (April-July 2009)
- Complete as many feature requests as possible in order of priority -- see bug tracker on Launchpad (all developers)
- Customization support (roles/tasks/fields) (Carl/Luke)
- Complete technical documentation and system administrator's manual (all developers)
- Clean up and productize code, including easy-install packages (all developers)
- Add in-context help and pop-up tips based on usability findings (developer TBD)
- Provide direct way to offer technical support from the software (developer TBD)
- Make user interface changes based on usability findings (developer TBD)
iHRIS Survey (Tentative Product Idea)
iHRIS Survey would enable the user to create a form with all needed fields, enter the data into a flat database and then run reports on that data. The form could be customized to address a variety of issues: backlog data entry; a step solution to prepare and clean data before importing into the mature HRIS; enter people or facility survey data; or any other form/database needs. If approved, the first iteration can be released in Summer 2009.
Q1-Q2 2009 Goals (January-April 2009)
Version 3.3:
- Duplicate records check (Carl)
- Import/export data function for Manage/Qualify and synchronization for offline version (Carl/Luke)
- Add asterisk to denote all required fields for easier data entry (Luke)
- Revise explanatory text, instructions and some page views (Reports, Administer Database) based on usability findings (Carol/Luke)
Q3-Q4 2008 Goals (July 2008-December 2008)
- Enable translation support -- complete
- Bug fixes/minor releases as needed -- complete
Q2 2008 Goals (April-June)
- Customized report builder for Manage/Qualify (Carl) -- complete and released in version 3.1
- In-service training management module for iHRIS Manage completed (Carl) -- complete and released in version 3.1
- iHRIS Plan version 1.0 (Luke) -- released
March 2008 Goals
- Post version 3.0 download packages for iHRIS Manage and Qualify (Carl/Luke) -- complete
- Active Directory and other system integration for IntraHealth HRIS completed (Mark + internal ICT support) -- complete
- Piloting and debugging of offline access (Mark) -- complete
February 2008 Goals
- iHRIS Plan specifications complete (Shannon) -- complete
- Update and post v3.0 documentation and user's manuals for Manage and Qualify (Shannon) -- complete
- Upgrade to version 3.0 of iHRIS Qualify in Uganda (Luke) -- complete
- Upgrade to version 3.0 of iHRIS Manage in Rwanda (Mark)
January 2008 Goals
- Version 3.0 RC1 coding completed and made available for bug testing (Carl/Luke) -- complete
- Test new features for version 3.0 of both systems (Shannon) -- complete
December 2007 Goals
- Prototype of Offline Access tool completed for initial testing (Mark) -- complete
- Workforce planning model approved for iHRIS Plan (Dykki) -- complete
November 2007 Goals
- Remaining first-round corrections to IntraHealth HRIS (Luke/Carl) -- complete
- Post updated versions of all existing documentation to website/wiki (Shannon) -- complete
- Complete specifications for training module for iHRIS Manage (Shannon) -- complete
October 2007 Goals
- Post the iHRIS Qualify Code to Launchpad (Luke) -- complete
- Post new feature requests on Launchpad for Manage and Qualify (Shannon) -- complete
- Print and export report/record feature (Carl) -- complete