Development Calendar: Difference between revisions

From IHRIS Wiki
(Updated goals for March-June and started adding Year 5 goals.)
Line 38: Line 38:
== Q2 2008 Goals (April-June) ==
== Q2 2008 Goals (April-June) ==


* Customized report builder for Manage/Qualify (Carl)
* Customized report builder for Manage/Qualify (Carl) ''estimated to be completed by the end of June''
* In-service training management module for iHRIS Manage completed (Carl) ''estimated to be completed by the end of June''
 
'''A 3.1 version of iHRIS Qualify and iHRIS Manage is planned for July 2008.'''
 
== Year 5 Goals (July 2008-December 2009) ==
 
Note: These goals needs to be prioritized and scheduled. Some goals may be deprioritized. They should not be considered final at this point.
 
* iHRIS Plan version 1.0 released (Luke)
* Customized roles for Manage/Qualify (Carl)
* Customized roles for Manage/Qualify (Carl)
* In-service training management module for iHRIS Manage completed (Carl)
* Import/export data function for Manage/Qualify based on similar function in offline version (developer TBD)
* Self-service access, supervisor/manager access and guest access to job application completed for IntraHealth's iHRIS Manage (Mark)
* Self-service access, supervisor/manager access and guest access to job application completed for IntraHealth's iHRIS Manage (Mark)
* iHRIS Plan version 1.0 released (Luke)
* Import/export data function for Manage/Qualify based on similar function in offline version (developer TBD)
=== Lower priority ===
These tasks may be pushed into the next fiscal year.
* Complete HRIS Inventory Assessment database prototype (Carl)
* Complete HRIS Inventory Assessment database prototype (Carl)
* Internationalization/translations support implemented in Manage/Qualify so that translations can begin (Carl)
* Internationalization/translations support implemented in Manage/Qualify so that translations can begin (Carl)
* Dual data entry support for Manage/Qualify (developer TBD)
* Dual data entry support for Manage/Qualify (developer TBD)

Revision as of 10:50, 13 June 2008

The following are development goals only, not necessarily hard-and-fast deadlines, and are subject to change. Expect this calendar to be updated frequently as new priorities come up. Developers, feel free to annotate with your own goals.


October 2007 Goals

  • Post the iHRIS Qualify Code to Launchpad (Luke) -- complete
  • Post new feature requests on Launchpad for Manage and Qualify (Shannon) -- complete
  • Print and export report/record feature (Carl) -- complete

November 2007 Goals

  • Remaining first-round corrections to IntraHealth HRIS (Luke/Carl) -- complete
  • Post updated versions of all existing documentation to website/wiki (Shannon) -- complete
  • Complete specifications for training module for iHRIS Manage (Shannon) -- complete

December 2007 Goals

  • Prototype of Offline Access tool completed for initial testing (Mark) -- complete
  • Workforce planning model approved for iHRIS Plan (Dykki) -- complete

January 2008 Goals

  • Version 3.0 RC1 coding completed and made available for bug testing (Carl/Luke) -- complete
  • Test new features for version 3.0 of both systems (Shannon) -- complete

February 2008 Goals

  • iHRIS Plan specifications complete (Shannon) -- complete
  • Update and post v3.0 documentation and user's manuals for Manage and Qualify (Shannon) -- complete
  • Upgrade to version 3.0 of iHRIS Qualify in Uganda (Luke) -- complete
  • Upgrade to version 3.0 of iHRIS Manage in Rwanda (Mark)

March 2008 Goals

  • Post version 3.0 download packages for iHRIS Manage and Qualify (Carl/Luke) -- complete
  • Active Directory and other system integration for IntraHealth HRIS completed (Mark + internal ICT support) -- complete
  • Piloting and debugging of offline access (Mark) -- complete

Q2 2008 Goals (April-June)

  • Customized report builder for Manage/Qualify (Carl) estimated to be completed by the end of June
  • In-service training management module for iHRIS Manage completed (Carl) estimated to be completed by the end of June

A 3.1 version of iHRIS Qualify and iHRIS Manage is planned for July 2008.

Year 5 Goals (July 2008-December 2009)

Note: These goals needs to be prioritized and scheduled. Some goals may be deprioritized. They should not be considered final at this point.

  • iHRIS Plan version 1.0 released (Luke)
  • Customized roles for Manage/Qualify (Carl)
  • Import/export data function for Manage/Qualify based on similar function in offline version (developer TBD)
  • Self-service access, supervisor/manager access and guest access to job application completed for IntraHealth's iHRIS Manage (Mark)
  • Complete HRIS Inventory Assessment database prototype (Carl)
  • Internationalization/translations support implemented in Manage/Qualify so that translations can begin (Carl)
  • Dual data entry support for Manage/Qualify (developer TBD)